B737 Normal Procedures: Engine Start, Taxi and Takeoff
The Boeing 737 engine start, taxi and takeoff procedures are the normal procedures that take the airplane from pushback to the After Takeoff checklist: pushback or towing, engine start, before taxi, before takeoff and takeoff, with the flap retraction speed schedule flown from the acceleration height.
The Boeing 737 engine start, taxi and takeoff procedures take the airplane from the gate to the After Takeoff checklist. Each is a flow done from memory and confirmed by a checklist, with most steps tied to a light, an indication or a callout.
This article follows the 737 NG flight crew operations manual (FCOM), chapter NP.21, and says where the 737 MAX differs; an operator's own procedures, built on Boeing's, govern its crews. The pilot flying (PF) taxis and controls the flight path, airspeed and configuration; the pilot monitoring (PM) reads the checklists, communicates and monitors (see pilot flying and pilot monitoring). The procedures before engine start are in B737 preflight and before start procedures, the climb onward in B737 descent, approach, landing and shutdown.
Pushback or towing
Boeing's procedures assume coordination with the ground crew before hydraulic pressurization, flight control movement or airplane movement. Normal nose wheel steering is powered by hydraulic system A. A nose gear steering lockout pin in the towing lever depressurizes the steering, so that the airplane can be pushed or towed without depressurizing the hydraulic systems.
The before start procedure therefore checks the pin when a pushback is needed. If it is not used, system A must not be pressurized, because unwanted tow bar movement can occur: its pumps stay OFF, the system B electric pump goes ON, and the brake and system B pressures must reach 2,800 psi. Otherwise both electric pumps go ON (see B737 hydraulic system).

During the pushback procedure two cautions apply. The crew must not hold or turn the nose wheel steering wheel, and must not use the airplane's brakes to stop it; either can damage the nose gear or the tow bar. When the pushback or tow is complete, the crew verify that the tow bar is disconnected and the lockout pin removed, switch the system A pumps ON, check that their LOW PRESSURE lights are out and that system A shows at least 2,800 psi.
Engine start procedure
The 737's air turbine starter needs pressurized air, from the APU, a ground cart or the other engine, and electrical power. The engine start switch at GRD uses battery power to close the engine bleed valve and open the start valve. The packs are switched OFF for the start, leaving the starter the full duct pressure. The ignition select switch, IGN L or IGN R, is alternated on successive starts; on most variants the left igniter is powered from its AC transfer bus and the right one from the AC standby bus. For the first flight of the day at airports at or above 2,000 ft with a temperature below 5 °C, the crew may consider BOTH to improve the chance of a first-time start.
The engine start procedure on the NG runs as follows:
- The captain calls "START ENGINE [number]" and sets the ENGINE START switch to GRD. N2 must increase, and the amber START VALVE OPEN alert shows the start valve open.
- When N1 rotation is seen and N2 reaches 25 %, the engine start lever goes to IDLE. If 25 % cannot be reached, it goes to IDLE at maximum motoring, when N2 gains less than 1 % in about 5 seconds, with at least 20 % N2. The lever energizes the ignition through the EEC and opens the spar and engine fuel shutoff valves.
- Light-up shows as an EGT rise, which must come within 15 seconds.
- At 56 % N2 the ENGINE START switch returns to OFF, or is moved there, START VALVE OPEN goes out and the crew call "STARTER CUTOUT".
- The engine is stable at idle when the EGT start limit redline is no longer shown.
| ENGINE START switch | Function |
|---|---|
| GRD | Opens the start valve, closes the engine bleed valve, arms the selected igniters for start lever IDLE (both in flight); releases to OFF at starter cutout |
| OFF | Ignition off; both igniters fire with the lever at IDLE on a rapid N2 decrease, with N2 between 57 % and 50 %, or in flight between idle and 5 % |
| CONT | Ignition to the selected igniters with the engine running |
| FLT | Ignition to both igniters |

Three warnings frame the start. A start lever moved to IDLE early can cause a hot start. If fuel is cut off by accident with the start lever, the lever is not reopened to try to restart the engine. If the switch fails to stay at GRD until starter cutout, a hot start can follow, and it is not re-engaged until N2 is below 20 %. Each start attempt is limited to 2 minutes of starter use, with at least 10 seconds between attempts; extended motoring is limited to 15 minutes for the first two runs, 2 minutes apart, then 5 minutes, 10 minutes apart.
Aborted start
The ABORTED ENGINE START checklist is done for a hung start, in which N1 or N2 does not increase, or increases very slowly, after the EGT rises; no oil pressure by the time the engine is stable at idle; no EGT rise within 15 seconds of the start lever reaching IDLE; or an EGT quickly nearing or exceeding the start limit. Its only recall item is the start lever to CUTOFF. The EEC also watches ground starts. It flashes the white box around the EGT readout for an impending hot start or a stall, and with EEC software 7.B.Q or later it then cuts the ignition and fuel itself. It also cuts them when EGT exceeds the start limit, which turns the EGT display red, and in a wet start, with no EGT rise, 15 seconds after the lever reaches IDLE. A red warning or amber caution during or after the start calls for the non-normal checklist, and on the ground the dispatch deviation guide.
On the 737 MAX the LEAP-1B engines replace the CFM56-7B, and the FAA FSB grades them as a Level B difference with a procedure change; start figures should come from the MAX FCOM rather than the NG's (see B737 engines and engine indications).
Before taxi procedure
The before taxi procedure starts once the engines are stable at idle. The generators go ON, probe heat ON and wing and engine anti-ice as needed. The packs return to AUTO and the isolation valve to AUTO, the APU bleed and then the APU are switched OFF, and the ENGINE START switches go to CONT, since ignition is required for takeoff and landing, in heavy rain and with anti-ice on. The start levers are checked in the IDLE detent. The flap lever is set to the takeoff flaps, with the green LE FLAPS EXT light on.
The flight controls check uses slow, deliberate inputs, one direction at a time. The control wheel, the column and the rudder pedals go to full travel each way, checking freedom of movement, the return to center and, if the surface positions are displayed on the lower display unit, the correct surface movement. The nose wheel steering wheel is held during the rudder check to keep the nose wheel still. A recall then shows every system annunciator light coming on and going out.
The PF taxis; the nose wheel steering wheel turns the nose wheels up to 78° either way; the rudder pedals give up to 7°, a limited authority deactivated as the nose gear strut extends. CDU entries are made before taxi or when stopped where possible; during taxi the PM makes them and the PF verifies them before execution.
Before takeoff procedure
The engines must be warm: the requirement is an increase in engine oil temperature before takeoff; Boeing recommends running the engines for at least 2 minutes at a thrust normally used for taxi. The pilot who will make the takeoff updates the takeoff briefing for any change, and the weather radar and terrain displays are set as needed. The cabin crew are told to prepare for takeoff, the cabin is confirmed secure, and the Before Takeoff checklist follows.
The last defense is the takeoff configuration warning. On the ground, as either forward thrust lever is advanced for takeoff, it sounds an intermittent horn and lights the red TAKEOFF CONFIG lights if the trailing edge flaps are outside the flaps 1 to 25 range or have a skew, asymmetry or uncommanded motion, if the leading edge devices are not in takeoff position or have moved uncommanded, if the speed brake lever is not DOWN, if the spoiler control valve is open, if the parking brake is set or if the stabilizer trim is outside the takeoff range. The FCOM warns that the cabin altitude warning uses the same intermittent tone. Fuel matters too: the random imbalance between main tanks 1 and 2 may not exceed 453 kg for taxi, takeoff, flight or landing.
Takeoff procedure
Before entering the departure runway the crew verify that it is the correct runway and entry point. On entering it the STROBE lights go ON, other lights as needed, and the transponder to TA/RA; when cleared for takeoff the FIXED LANDING lights go ON on most variants.

The PF advances the thrust levers to about 40 % N1, lets the engines stabilize, pushes a TO/GA switch and verifies that the correct takeoff thrust is set. With the flight directors on, TO/GA engages the takeoff modes, the pitch command showing 10° nose down until 60 kt and 15° nose up after. Any thrust adjustment is made before 60 kt, by hand if strong headwinds stop the levers short of the planned thrust. From 84 kt the autothrottle shows THR HLD. The captain keeps a hand on the thrust levers until V1 (see takeoff procedures and rejected takeoff).
| Event | PM | PF |
|---|---|---|
| 80 kt | "80 KNOTS" | Verifies, "CHECK" |
| V1 | Verifies the automatic callout or calls "V1" | |
| VR | "ROTATE" | Rotates toward 15° pitch |
| Positive climb | "POSITIVE RATE" | "GEAR UP"; PM selects UP |
After liftoff the PF follows the flight director, which keeps 15° nose up until the climb rate is sufficient and then commands the MCP speed, normally V2, plus 20 kt. Above 400 ft radio altitude the crew select a roll mode as needed and verify VNAV engaged; below 400 ft the takeoff mode can only be ended by switching both flight directors off. The autopilot may not be engaged below 400 ft AGL. In a normal takeoff the autothrottle stays in THR HLD until 800 ft above field elevation, then shows ARM. At the thrust reduction height the crew verify that climb thrust is set, and at the acceleration height the PF verifies acceleration and calls for the flaps on schedule.
On the 737 MAX, the FSB special training includes an erroneous high angle of attack during takeoff that leads to unreliable airspeed, continued into a go-around or missed approach, with special emphasis on the flight director bars biasing out of view when TO/GA is selected.
Flap retraction speed schedule
The flap retraction speed schedule retracts the flaps in steps: each new position is selected when the speed reaches the green flap maneuvering speed bug of the position just selected, shown on the speed tape. The bank angle is limited to 15° until V2 + 15.
| Takeoff flaps | At V2 + 15 | Then |
|---|---|---|
| 25 | Select 15 | At "15" select 5; at "5" select 1; at "1" select UP |
| 10 or 15 | Select 5 | At "5" select 1; at "1" select UP |
| 5 | Select 1 | At "1" select UP |
| 1 | At "1" select UP |
The white V2 + 15 bug is removed at the first flap retraction, which also brings up the minimum maneuver speed bar (see B737 flight instruments and displays and B737 flaps and leading edge devices). On the MAX, retraction has another consequence: MCAS works only with the flaps up in manual flight, and the split vane monitor that compares the two angle of attack inputs is active only once the flaps are retracted.
After takeoff
When flap retraction is complete, the crew set or verify that the engine bleeds and packs are operating, set the engine start switches as needed and the AUTO BRAKE select switch to OFF. On the NG the landing gear lever goes to OFF once gear retraction is complete. The 737 MAX lever has only two positions, so there is no OFF to select; the FSB lists the changed After Takeoff checklist as a Level B difference and makes gear handle operation an item of special emphasis. The After Takeoff checklist completes the phase, and the climb and cruise procedure begins after it.

Exam tip: know 25 % and 20 % N2 (start lever to IDLE), 15 seconds (EGT rise), 56 % N2 (starter cutout), 2 minutes and 10 seconds (starter duty), 40 % N1 (before TO/GA), 60 kt (last thrust adjustment), 84 kt (THR HLD), 400 ft (roll mode, autopilot) and 15° of bank until V2 + 15.
Frequently asked questions
When is the start lever moved to IDLE during a 737 engine start?
On the 737 NG, once N1 rotation is seen and N2 has reached 25 percent. If 25 percent is out of reach, the lever goes to IDLE at maximum motoring, when N2 gains less than 1 percent in about 5 seconds, as long as N2 is at least 20 percent. Moving it earlier can cause a hot start. The starter then keeps turning the engine until about 56 percent N2, when the ENGINE START switch returns to OFF.
What are the Boeing 737 starter duty cycle limits?
For normal starts, several consecutive attempts are allowed, each limited to 2 minutes of starter use, with at least 10 seconds between attempts. For extended engine motoring, the first two motorings may last up to 15 minutes each with at least 2 minutes between them; the third and later ones are limited to 5 minutes each, with at least 10 minutes between them.
How is takeoff thrust set on the Boeing 737?
The thrust levers are advanced to about 40 percent N1, the engines are allowed to stabilize and a TO/GA switch is pushed, after which the crew verify that the correct takeoff thrust is set. Any adjustment is made before 60 knots, by hand if strong headwinds stop the levers short of the planned thrust. The autothrottle shows THR HLD from 84 knots, and the captain keeps a hand on the thrust levers until V1.
What is the Boeing 737 flap retraction schedule after takeoff?
From the acceleration height the flaps are retracted step by step as the speed reaches each flap maneuvering speed on the speed tape. From flaps 25, flaps 15 is selected at V2 + 15, then 5, 1 and UP. From flaps 10 or 15, flaps 5 at V2 + 15, then 1 and UP. From flaps 5, flaps 1 at V2 + 15, then UP, and from flaps 1, UP. Bank is limited to 15 degrees until V2 + 15.
What do the 737 ENGINE START switch positions do?
GRD opens the start valve, closes the engine bleed valve and arms the selected igniters for when the start lever reaches IDLE; a solenoid holds it there until starter cutout. OFF leaves the ignition off, although both igniters fire if a rapid N2 decrease or another flameout condition is detected. CONT gives ignition to the selected igniters while the engine runs, and FLT gives ignition to both igniters.
Why is the nose gear steering lockout pin used for a 737 pushback?
Fitted in the towing lever, the pin depressurizes the nose wheel steering, so the airplane can be pushed or towed with its hydraulic systems pressurized. Without it, hydraulic system A, which powers normal nose wheel steering, must stay depressurized, because unwanted tow bar movement can occur. After pushback the crew verify that the tow bar is disconnected and the pin removed, then switch the system A pumps on.
Test yourself on B737 Normal Procedures: Engine Start, Taxi and Takeoff
The v1prep banks cover this topic in the B737 type-rating bank, with a worked explanation for every answer. EASA ATPL, PPL, IR and CPL, the FAA written tests and type ratings for the A320, 737, A220, 787, ATR 72 and E-Jet.
Start practicing →Sources and further reading
- FAA Flight Standardization Board Report, Boeing 737, Revision 17
- EASA Type Certificate Data Sheet IM.A.120, Boeing 737
- FAA, Summary of the FAA's Review of the Boeing 737 MAX (November 2020)
- FAA AC 120-71B, Standard Operating Procedures and Pilot Monitoring Duties
- FAA Aviation Maintenance Technician Handbook, Powerplant (FAA-H-8083-32B), Engine Starting Systems
- FAA, Pilot Guide to Takeoff Safety
Library articles are written for study and exam preparation. They do not replace your aircraft's approved documentation, your operator's procedures or the regulations themselves.